    How Long Does It Take to Develop a Multifamily Project in San Diego?

    By Ground Zero Development•

    A typical San Diego multifamily project of up to 20 units takes 24 to 36 months from first consultation to delivery. Most of that time is spent in two phases: entitlements and permitting (9 to 12 months) and construction (12 to 18 months).

    Key takeaways

    • The full path runs 24 to 36 months from consultation to delivery for projects of up to 20 units.
    • Feasibility takes about 1 month, and design takes 3 to 4 months.
    • Entitlements and permitting take 9 to 12 months, and construction takes 12 to 18 months after that.
    • Stabilization adds 3 to 6 months after construction.
    • Modeling zoning, unit count, rents, and construction costs first protects you from paying for design on a project that doesn't pencil.

    The five phases of a San Diego multifamily project

    Ground Zero Development runs every phase of a project with one accountable team. Here is how the time breaks down.

    PhaseTypical durationWhat happens
    Acquisition and feasibilityAbout 1 monthReview of the lot: maximum buildable units, estimated budget, projected rent
    Design3 to 4 monthsArchitecture and planning, with zoning, unit count, rents, and cost modeled first
    Entitlements and permitting9 to 12 monthsCity review and approvals before construction can start
    Construction12 to 18 monthsPhase-by-phase build against a schedule set at the start
    Stabilization3 to 6 monthsLease-up and property management setup so the building performs

    Most projects fall within these ranges. What changes from project to project is how much time each stage takes.

    Phase 1: Acquisition and feasibility (about 1 month)

    Acquisition starts with a feasibility review of the lot. The owner sends a San Diego address, and Ground Zero reports the maximum buildable units, an estimated budget, and projected rent. The review is free and carries no obligation, and the first answer comes back within 2 business days. Full feasibility takes about a month.

    This step shows what the lot can support before you commit capital.

    "Once we're past the initial feasibility, we dive deeper into not just what can be built, but what should be built and how it will perform. A large part of the pre-development stage that follows feasibility is assessing what the right product is to build for the market it will exist in." Carl Dumesle, CEO, Ground Zero Development

    Phase 2: Design (3 to 4 months)

    Ground Zero works with ohms architects, a full-service architecture, design, and research office in San Diego, to plan each project. Ground Zero first models zoning allowances, achievable unit count, comparable rents, and construction costs. The project is proven on paper before design spend begins.

    Phase 3: Entitlements and permitting (9 to 12 months)

    This is the longest stretch before the shovel hits the ground. The project goes through City review and approvals. The time depends on project size, site conditions, and City review queues.

    "Most people think that the construction phase carries the most risk, but we believe that entitlement risk trumps it. Here, we're working on more than the single permit to build a new structure; there's a slew of other filings and follow-ups needed before a project is shovel-ready." Carl Dumesle, CEO, Ground Zero Development

    Phase 4: Construction (12 to 18 months)

    Construction runs 12 to 18 months after entitlements and permitting are complete. BuildingSD, a San Diego residential design-build firm focused on ADUs and multifamily construction, manages the build. Ground Zero reports progress against a phase-by-phase schedule set at the start.

    Phase 5: Stabilization (3 to 6 months)

    After construction, the property needs to lease up and settle into operations. Parkside, a San Diego property management firm serving real estate investors and developers, manages this stage. The goal is a completed property positioned to lease and perform.

    What affects your timeline

    • Project size and complexity. Larger and more complex projects sit toward the long end of each range.
    • City review queues. Entitlements and permitting are the least predictable phase.
    • Site conditions. Existing structures, access, and utilities can add time.
    • Decisions made early. Proving the numbers before design reduces redesign loops later.
    • Owner decision speed. Fast feedback from the owner keeps each stage moving.

    Frequently asked questions

    How long does a multifamily development take in San Diego?
    A typical project of up to 20 units takes 24 to 36 months from consultation to delivery: about 1 month for feasibility, 3 to 4 months for design, 9 to 12 months for entitlements and permitting, and 12 to 18 months for construction. A 3 to 6-month stabilization period follows.
    Which phase takes the longest?
    Construction takes the longest at 12 to 18 months, followed by entitlements and permitting at 9 to 12 months.
    How long does a feasibility review take?
    Ground Zero reports maximum buildable units, an estimated budget, and projected rent within 2 business days. Full feasibility takes about 1 month. The review is free and carries no obligation.
    Who manages each phase?
    Ground Zero Development leads the process. ohms architects handles design planning, BuildingSD manages construction, and Parkside manages stabilization.
    Can the timeline be shortened?
    Yes, and the biggest lever is how quickly decisions get made. Carl Dumesle, CEO of Ground Zero Development, says: "What moves the needle the most in projects that move fast is the speed of decision-making. The owners who provide their feedback quickly are the ones who win the most."

    Next step

    Have a San Diego lot and want to know what it can support? Request a free feasibility review, or learn more about White Glove Development. See our portfolio for San Diego multifamily projects Ground Zero has built.

    Ground Zero Development is a San Diego real estate developer that builds ground-up multifamily and ADU projects and legalizes unpermitted construction through retroactive permitting.